Eastern lays keel for second OPC
Eastern Shipbuilding Group Inc. (ESG), Panama City, Fla., yesterday hosted the keel authentication ceremony for the second vessel in the U.S. Coast Guard’s new offshore patrol cutter (OPC) program, the future USCGC
Eastern Shipbuilding Group Inc. (ESG), Panama City, Fla., yesterday hosted the keel authentication ceremony for the second vessel in the U.S. Coast Guard’s new offshore patrol cutter (OPC) program, the future USCGC
A new GAO (Government Accountability Office) report into the U.S. Coast Guard’s Offshore Patrol Cutter (OPC) program is critical of several aspects of the acquisition strategy and makes eight recommendations that, it
Face masks and social distancing were much in evidence when the Coast Guard and Eastern Shipbuilding Group (ESG) authenticated the keel for the first Offshore Patrol Cutter (OPC), Argus, at a ceremony
The U.S. Coast Guard modified its contract with Eastern Shipbuilding Group (ESG) April 2 to begin construction of the second Offshore Patrol Cutter (OPC) and to acquire long lead-time material (LLTM) for
Following the Department of Homeland Security decision to make changes in its Offshore Patrol Cutter contract with Eastern Shipbuilding, the U.S. Coast Guard has released a request for information (RFI) to gauge
The Department of Homeland Security is easing the time deadlines in Eastern Shipbuilding’s Offshore Patrol Cutter contract, but only on the first four hulls. After that, it says, “The Coast Guard will
The U.S. Coast Guard is set to award the contract for the first Polar Security Cutter in the very near future. Giving the 2019 State of the Coast Guard address at Coast
NOVEMBER 2, 2018 — Eastern Shipbuilding Group, Inc. reports that it has resumed operations at both of its two main shipbuilding facilities just two weeks after Hurricane Michael devastated Panama City, Florida,
SEPTEMBER 28, 2018 — The U.S. Coast Guard today exercised contract options with Eastern Shipbuilding Group to begin construction of the lead offshore patrol cutter (OPC), Argus, and to acquire long lead-time
JULY 12 2018 — Panama City, FL, based Eastern Shipbuilding Group and the U.S. Coast Guard successfully conducted the Final Critical Design Review (FCDR) for the Offshore Patrol Cutter (OPC) Program on