sea trials

NSC 10 on trials

NSC 10 completes builder’s sea trials

Huntington Ingall Industries’ Ingalls Shipbuilding division reports that NSC 10, the U.S. Coast Guard’s tenth and newest national security cutter, Calhoun (WMSL 759) has now completed builder’s sea trials The ship successfully

VIDEO: Silver Moon completes sea trials

Royal Caribbean Group’s ultra luxury brand Silversea Cruises reports that its ninth ship, Silver Moon successfully carried out her sea trials between August 8 and August 20, traveling between Fincantieri’s Ancona, Italy,

  • News

CVN 78 sea trials delayed

The Navy and shipbuilder, Newport News Shipbuilding had scheduled a delivery date of March 31, 2016 for the ship. That will now likely slip  to mid- or late-May.

In its statement yesterday, the Navy said “the sea trial schedule will be delayed about six to eight weeks. The exact impact on ship delivery will be determined based on the results of sea trials.The Navy called the delay a “prudent step” providing “the most affordable path to delivery. All the work and any associated schedule delays are being managed within budget and below the $12,887 million cost cap.”

The Navy did not say what particular part of the test program has gotten behind schedule.

It did note that significant progress to date has been made on CVN 78, including:

  • EMALS testing was successfully completed on the bow catapults and proceeding on schedule to complete in November on the waist catapults
  • The crew moved aboard as scheduled in August and is living and feeding aboard. Compartment turnover to the crew remains on track.
  • Dual Band Radar (DBR) testing has commenced including initial energization of Multifunction Radar/ Volume Search Radar (MFR/VSR) array faces
  • The propulsion plants have completed their non-critical steaming program and are preparing for their critical test program

CVN 78 is 93% complete.