Cashman completes Boston Harbor Phase II dredging almost one year ahead of schedule

Written by Marine Log Staff
image description

Cashman Dredging' clamshell dredge at work on Boston Harbor Phase II deepening project

New England’s busiest port is closer to welcoming larger containerships and growing the regional economy with the completion of Phase II of the U.S. Army Corps’ Boston Harbor Navigation Improvement Project by Cashman Dredging and its joint venture partner, the Dutra Group.

Completed last month, nearly one year ahead of schedule, Phase II of the project began in July of 2018 and focused on deepening the main ship channels: the Outer Harbor Channel from 40 to 51 feet, the Main Shipping Channel from 40 to 47 feet, and the Reserve Channel from 40 to 47 feet.

Boston Harbor’s Conley Container Terminal, which currently handles 10,000 TEU vessels, will now be able to accommodate with reduced tidal delays 12-14,000 TEU vessels calling on the U.S. East Coast, bringing more commerce to the state and region.

Working 24/7/365, the Cashman/Dutra JV removed approximately 12 million cubic yards of silt, Boston blue clay, glacial till and weathered rock over a seven-mile area with Cashman Dredging’s clamshell dredges Dale Pyatt, FJ Belesimo, and backhoe dredge Captain AJ Fournier, as well as the Dutra Group’s clamshell dredge Paula Lee.

Seven split-hull dump scows were used to transport the dredged material to Mass Bay Disposal Site, located approximately 20 nautical miles from the project.

To help overcome the hard material in the channel and increase efficiency on the project, Cashman Dredging designed and built in-house a new ripper barge and purchased two 33-cubic yard buckets weighing 80,000 pounds. The company also installed its in-house designed Scow Geofence System (SGS) to add an additional layer of quality control to material disposal via split-hull scow. The SGS prevents scows from inadvertently opening during loading, maintenance, or transit to the dredged material disposal site. Using a relay to connect the SGS to the programmable logic controller, the scow must be positioned within the predefined area, the geofence, for it to split open and dispose the material.

The high-traffic nature of the harbor, paired with its proximity to Boston Logan International Airport, made the project especially complex. It required extensive coordination with many parties, including Massport Aviation, Logan Airport Air Traffic Control, and the Federal Aviation Administration, which restricted drone, sonar, and video footage.

Winter weather and ice buildup on the dredges and cranes presented daily safety challenges for the crews.

Deer Island’s directionally drilled power lines, along with existing power lines in the dredging footprint, called for a heightened state of awareness and implementation of best practices for dredging near underwater utilities.

Further coordination was also required with the U.S Army Corps of Engineers, U.S. Coast Guard, Boston Pilots Association, commuter ferries, lobstermen, recreational users, and many others.