• News

Siemens installs North Sea offshore wind platform

Written by Nick Blenkey

helwin alphaAUGUST 26, 2013 — Siemens has installed the HelWin1 offshore platform in the North Sea, marking the successful completion of a significant stage in Germany’s offshore wind power grid connection projects.

After seven days of transport at sea and four days of installation on site, the HelWin1 platform was anchored at its final position northwest of the island of Helgoland on August 23. Siemens had installed the platform’s support substructure at the 23 m deep location in June when ten steel pilings up to 3.2 meters in diameter and with a wall thickness of eight centimeters were anchored in the seabed. With a length of up to 100 meters, these pilings are as tall as London landmark Big Ben.

The platform is installed 22 meters above sea level to protect it against giant waves.

HelWin1 is designed for decades of operation in the rugged North Sea.

The platform is equipped with a helipad and was fabricated by Nordic Yards at its shipyard in Wismar under contract by Siemens. Nordic Yards has been contracted by Siemens for the fabrication of two more HVDC platforms for the grid connections BorWin2 and SylWin.

At 12,000 tons, the HelWin1 platform weighs more than 20 loaded and fully fueled Airbus A380 aircraft. The surface area of the platform, at 75 by 50 meters, is more than half the size of a soccer field. The platform’s seven decks, spanning a total height of 27 meters, accommodate 16 cabins for crew members with a total of 24 berths, a galley, sanitary facilities, a multi-purpose room equipped with sports equipment and a day room with satellite TV, in addition to housing all the technology and equipment required for HVDC transmission.

Up to 100 employees will be active on the platform for the subsequent project phase in the North Sea. They will first re-open the doors and panels previously welded closed for transport and remove other protective transport fixtures and ballast weights. An on-site jack-up platform.Two subsea cables from Prysmian are also to be connected. Siemens’ consortium partner has supplied and laid in bundle the two cables, each with a length of 130 km, for transmission of 250 kilovolt DC voltage in the future. The cable route covers 85 km at sea and 45 km over land. Both 11 cm thick cables, with its protective steel armoring wire layer and a 35 mm thick copper conductor, weighs about 30 kg per meter.

The HelWin1 HVDC platform has a capacity of 576 megawatts (MW). Thanks to the efficient direct-current technology employed, the total transmission losses for this connection are less than four percent. The HVDC Plus technology employed by Siemens reduces the complexity and, hence, the space requirements for HVDC systems, which is a decisive factor for installation at sea. In contrast to classic HVDC technology used in a vast majority of land links, systems equipped with HVDC Plus feature self-stabilization. This enhances grid reliability in the event of power fluctuations, which can occur with wind-based power generation. HVDC Plus is a multi-level VSC system. This modular, multi-level VSC technology ensures an almost ideal sinusoidal AC waveshape and smoothed direct voltage along the transmission line, that makes the installation of high-frequency and harmonic filters practically superfluous, says Siemens.

The commissioning of HelWin1 is scheduled for the second half of 2014. The platform is completely automated and the systems on the platform can be monitored and controlled from land, with cameras and sensors providing a complete overview of the current operating status. The crews’ quarters on the platform can be used when maintenance work is required. Siemens was contracted by TenneT for maintenance of the grid connection for an initial period of five years.

HelWin1 will link two offshore wind farms, Nordsee Ost and Meerwind, to the mainland. Using the Siemens technology installed on the platform, the alternating current power generated by the wind turbines is transformed into low-loss direct current for transmission onto land.

Starting next year, this will enable the network operator and purchaser TenneT to supply electricity to more than 500,000 mainland households. The land-based station, also supplied by Siemens to TenneT, is located northwest of Hamburg in Büttel, where electricity will be converted back into the alternating current power required for feeding into the grid.

“With the installation of our platform at sea we have successfully mastered the most critical part of this project and are now in the final stretch for commissioning in 2014”, said Karlheinz Springer, CEO of the Power Transmission Division of Siemens Energy Sector.

Network operator TenneT contracted a consortium consisting of Siemens and the Italian cable specialist Prysmian for the HelWin1 offshore grid connection in 2010. The consortium is implementing a total of four North Sea grid connection projects for TenneT; HelWin1 and HelWin2 off of Helgoland, BorWin2 off of Borkum and SylWin1 off of Sylt.

Categories: News Tags:

Leave a Reply