• News

GAO report slams Navy cruiser modernization efforts

Written by Nick Blenkey
GAO report looks at cruiser modernization

Image: GAO

The U.S. Government Accountability Office (GAO) has released a report that is sharply critical of a Navy cruiser modernization program that began when Congress rejected Navy proposals made in 2012 and 2013 to retire several of the ships and instead provided funding to modernize them.

In response, says GAO, the Navy planned to use a phased approach to modernization that would extend 11 cruisers’ service life by five years and upgrade the vessels’ combat capability. The Navy originally planned to complete all 11 cruisers by fiscal year 2026. The Navy has other upcoming significant surface ship modernization efforts, such as for 23 destroyers. The success of these efforts is critical to the Navy having a combat-ready fleet.

WHAT GAO FOUND

Since 2015, says GAO, the Navy has spent about $3.7 billion modernizing seven of the Ticonderoga class guided-missile cruisers—large surface combatants that provide key air defense capabilities. However, only three of the seven ships will complete modernization, and none will gain five years of service life, as intended.

The Navy wasted $1.84 billion modernizing four cruisers that have now been divested prior to deploying. The Navy also experienced contractor performance and quality issues across the cruiser effort. For example, the contractor performed poor quality work on USS Vicksburg’s sonar dome—a critical element of the Anti-Submarine Warfare mission area—resulting in additional cost and schedule delays due to necessary rework.

cruiser modernization graphic
Status of Navy cruiser modernization as of August 2024

GAO says that the Navy did not effectively plan the cruiser modernization effort. This led to a high volume of unplanned work–9,000 contract changes–resulting in cost growth and schedule delays. The Navy has yet to identify the root causes of unplanned work or develop and codify root cause mitigation strategies to prevent poor planning from similarly affecting future surface ship modernization efforts.

“Further, weakened quality assurance tools restricted the Navy’s ability to hold contractors accountable for poor quality work,” says GAO. “In 2018, leadership restricted maintenance officials from assessing monetary penalties to contractors without senior leadership approval. In 2020, leadership changed procedures to reduce inspections, which are a vital tool for overseeing ship repair contracts, by almost 50%. These actions were implemented to maintain strong working relationships with the contractors because of the Navy’s dependence on them to modernize its fleet, according to Navy officials. Without reassessment, the Navy risks experiencing similar negative outcomes in future modernization efforts.”

RECOMMENDATIONS

GAO is making six recommendations, including that the Navy assess root causes of unplanned work, develop mitigation strategies, and codify these strategies in policy; and re-assess its overall approach to quality assurance to prevent similar issues in future surface ship modernization efforts. The Navy concurred with all six recommendations.

  • Download the full GAO report HERE
Categories: News Tags: , , ,