offshotre wind pause

Battle against latest U.S. offshore wind pause reaches courts

Inevitably, offshore wind developers are looking to the courts to overturn the pause imposed by the Department of the Interior on Dec. 22, 2025 on the leases for all large-scale offshore wind

Wind farm Northeasr governors

Northeast governors demand end to latest pause on offshore wind

New York Gov. Kathy Hochul, Connecticut Gov. Ned Lamont, Massachusetts Gov. Maura Healey and Rhode Island Gov, Dan McKee have written Secretary of the Interior Doug Burgum demanding the immediate lifting of

CableCable burial vessel [Image: Mitsui O.S.K. Lines]

ClassNK grants AiP to two MOL cable vessel designs

ClassNK has issued an Approval in Principle (AiP) for the designs of a cable jointing vessel and a cable burial vessel developed by Mitsui O.S.K. Lines Ltd (MOL). The certification demonstrates the

Light well intervention vessel Seawell [Photo: Helix Energy Solutions]

Helix Energy Solutions awarded multi-year North Sea plug & abandonment contract

Houston-headquartered Helix Energy Solutions Group, Inc. (NYSE: HLX) reports that it has secured a multi-year contract with a major operator for riserless plug and abandonment (P&A) operations on up to 34 subsea

radar clutter cited in putting new pause on offshore wind

Trump Administration cites radar clutter in putting new pause on offshore wind projects

In another assault on the U.S. offshore wind industry, the Department of the Interior announced today that it is pausing—effective immediately—the leases for all large-scale offshore wind projects under construction in the

WTIV row resolved

Seatrium and Maersk Offshore Wind resolve WTIV delivery dispute

Singapore-headquartered Seatrium Limited reported today that its Seatrium Energy (International) Pte Ltd unit (SEI) and Maersk Offshore Wind affiliate Phoenix II A/S have resolved a dispute that began back in October when

Windward Athens is fitted withScanReach ConnectPOB

Windward Offshore opts for ScanReach ConnectPOB for newbuild CSOV quartet

Straume, Norway, headquartered ScanReach reports that its ConnectPOB personnel-on-board and safety platform has been selected for the series of four newbuild Commissioning Service Operation Vessels (CSOVs) ordered by Hamburg-headquartered Windward Offshore from

DP2 effectiveness was demonstrated in sea trials ofDEME wind turbine installation vessel (WTIV) Norse Wind. [Image: ABB/DEME]

Trials on DEME WTIV verify benefits of ABB’s new DP2 functionality

ABB reports that it has verified a major advance in vessel dynamic positioning (DP) technology, following successful Failure Mode and Effects Analysis (FMEA) proving trials and sea trials on board the new

Trump offshore wind ban struck down

U.S. District Judge strikes down Trump halt on wind energy approvals

In a ruling in U.S. District Court for the District of Massachusetts, Judge Patti B. Saris yesterday struck down President Trump’s halt on approvals of all wind energy projects on federal lands

Crane simulator

Jan De Nul commissions new crane simulator for offshore wind farm installation

This month Jan De Nul will commission two high-tech simulators at its Aalst, Belgium office, one a crane simulator for offshore wind farm installation, the other a simulator for cutter suction dredge

LOAD MORE